SECRET Date: August 6, 1951 TO: Richard Gorrell FROM: Harvey Corbin RE: Ellis Island Budget On July 12th you were informed that the Ellis Islandproject is currently 1.6 million dollars over budget andyou were asked to submit (1.) a detailed explanation,including a list of overruns with an explantion foreach, (2.) a list of initiatives aimed at controlling costs,and (3.) a projected/revised budget for fiscal year 1951. For the reasons listed above I am suspending paymentof all bills associated with the Ellis Island project untilyou submit the documents outlined in paragraph one.